Background
Samaritan’s Purse Liberia intends to engage a qualified drilling service provider to carry out compressor airlifting (blow-out) and borehole development works on ten (10) completed village-drilled boreholes. The purpose of the exercise is to remove drilling residues, fine sediments, clay particles, and other foreign materials from the boreholes; improve aquifer connectivity; increase borehole yield; and ensure that each borehole produces clear and sustainable water suitable for hand pump installation and community use.
The Contractor shall provide all labor, equipment, compressor units, air hoses, fittings, transportation, fuel, personnel, tools, and incidental services necessary to complete the works in accordance with these specifications.
Please read carefully the Technical Specifications/Scope of Work for compressor airlifting (Blow out) of Boreholes:
The objective of the airlifting exercise is to:
The contractor shall perform the following activities for each borehole:
The contractor shall:
Before commencing airlifting operations, the Contractor shall:
No airlifting work shall commence without the presence and approval of the Employer’s Drilling Coordinator or Technical Officer.
The Contractor shall carry out borehole development using a high-capacity air compressor capable of delivering sufficient air pressure and volume to effectively clean and develop the borehole.
The development process shall include:
Development shall continue until:
Under no circumstances shall the Contractor stop development solely based on time allocation if the borehole remains inadequately developed.
For each borehole, the Contractor shall:
The Employer’s Drilling Coordinator or Technical Officer reserves the right to require additional development if results are unsatisfactory.
The Contractor shall ensure the complete removal of:
Any borehole showing continued sediment production shall undergo additional development until acceptable conditions are achieved.
During development, the Contractor shall:
Any abnormal borehole conditions shall be immediately reported to the Employer.
The Contractor shall provide:
Compressor
Airlifting Equipment
Personnel
At minimum:
All personnel shall have proven experience in rural water supply borehole development.
The following minimum standards shall apply:
Water Clarity
The Contractor shall continue development until water appears substantially clear and free from visible suspended materials.
Sand Content
Water discharged shall contain minimal sand.
Borehole Recovery
The borehole shall demonstrate adequate recovery after development.
Borehole Integrity
The Contractor shall ensure that development activities do not damage:
For each borehole, the Contractor shall submit:
Borehole Development Record
Including:
Photographic Documentation
The Contractor shall provide clear photographs showing:
Photographs shall be shared electronically with the Employer’s Technical Officer on the same day of operation.
No variation work shall be undertaken without written approval.
The Contractor shall:
A borehole shall only be accepted when:
Payment shall be based on successful completion and acceptance of each borehole and shall be subject to:
Failure to achieve satisfactory borehole development may result in rejection of the work and withholding of payment until corrective measures are completed.
The Contractor shall be responsible for any damage caused to the borehole arising from:
Any such damage shall be repaired by the Contractor at no additional cost to the Employer.
Special Instruction
The Employer’s Drilling Coordinator or Technical Officer must be present during all airlifting activities. No borehole shall be developed, altered, deepened, or subjected to additional works without prior approval from the Employer’s representative. All measurements, observations, and development records shall be jointly verified and signed before site demobilization.
Tender Bid Submission: from September 29, 2026 to October 9, 2026