Samaritan’s Purse Liberia intends to engage a qualified drilling service provider to carry out compressor airlifting (blow-out) and borehole development works on ten (10) completed village-drilled boreholes. The purpose of the exercise is to remove drilling residues, fine sediments, clay particles, and other foreign materials from the boreholes; improve aquifer connectivity; increase borehole yield; and ensure that each borehole produces clear and sustainable water suitable for hand pump installation and community use.
The Contractor shall provide all labor, equipment, compressor units, air hoses, fittings, transportation, fuel, personnel, tools, and incidental services necessary to complete the works in accordance with these specifications.
Please read carefully the Technical Specifications/Scope of Work for compressor airlifting (Blow out) of Boreholes:
The objective of the airlifting exercise is to:
The contractor shall perform the following activities for each borehole:
The contractor shall:
Before commencing airlifting operations, the Contractor shall:
No airlifting work shall commence without the presence and approval of the Employer’s Drilling Coordinator or Technical Officer.
The Contractor shall carry out borehole development using a high-capacity air compressor capable of delivering sufficient air pressure and volume to effectively clean and develop the borehole.
The development process shall include:
Development shall continue until:
Under no circumstances shall the Contractor stop development solely based on time allocation if the borehole remains inadequately developed.
For each borehole, the Contractor shall:
The Employer’s Drilling Coordinator or Technical Officer reserves the right to require additional development if results are unsatisfactory.
The Contractor shall ensure the complete removal of:
Any borehole showing continued sediment production shall undergo additional development until acceptable conditions are achieved.
During development, the Contractor shall:
Any abnormal borehole conditions shall be immediately reported to the Employer.
The Contractor shall provide:
Compressor
Airlifting Equipment
Personnel
At minimum:
All personnel shall have proven experience in rural water supply borehole development.
The following minimum standards shall apply:
Water Clarity
The Contractor shall continue development until water appears substantially clear and free from visible suspended materials.
Sand Content
Water discharged shall contain minimal sand.
Borehole Recovery
The borehole shall demonstrate adequate recovery after development.
Borehole Integrity
The Contractor shall ensure that development activities do not damage:
For each borehole, the Contractor shall submit:
Borehole Development Record
Including:
Photographic Documentation
The Contractor shall provide clear photographs showing:
Photographs shall be shared electronically with the Employer’s Technical Officer on the same day of operation.
No variation work shall be undertaken without written approval.
The Contractor shall:
A borehole shall only be accepted when:
Payment shall be based on successful completion and acceptance of each borehole and shall be subject to:
Failure to achieve satisfactory borehole development may result in rejection of the work and withholding of payment until corrective measures are completed.
The Contractor shall be responsible for any damage caused to the borehole arising from:
Any such damage shall be repaired by the Contractor at no additional cost to the Employer.
Special Instruction
The Employer’s Drilling Coordinator or Technical Officer must be present during all airlifting activities. No borehole shall be developed, altered, deepened, or subjected to additional works without prior approval from the Employer’s representative. All measurements, observations, and development records shall be jointly verified and signed before site demobilization.
Tender Bid Submission: from September 29, 2026 to October 9, 2026
Bidding Documents Required
All bidders must submit:
Minimum Requirements for Acceptance
Suppliers must:
Statutory
Operational Capacity
Technical Capacity
Financial Capacity
Price & Lead Time
Request for Quotation Documents – please send in an email to Liberia-Procurement@samaritan.org
Submission Instructions:
Please ensure you include all necessary documentation. Note that incomplete packages may not be considered for the award. Also, ensure your email size is LESS than 15MB. If sending multiple emails, please appropriately number each email (Example: 1/3, 2/3, 3/3, etc). You will receive an acknowledgement email if your bid was submitted correctly.
Optional Hard Copy Submission:
Samaritan’s Purse Office
ELWA Compound, Paynesville, Monrovia, Liberia
Closing Date: October 9, 2026 – 5:00 PM Liberia Time
(Late bids will be automatically disqualified.)
Important Notes
WE PRACTICE PROCUREMENT WITH INTEGRITY
The integrity of the Public Tender procurement process is of the utmost importance. Unethical procurement conduct will not be tolerated and will result in immediate dismissal from the Public Tender procurement process. All bids are received directly by the Tender committee. It is not possible to influence the decision or outcome of the Tender. Submit your best value proposal for the first and only time. No Samaritan’s Purse employee will solicit you outside of this tender.
If you, the supplier, suspect fraud from an SP employee, are asked to commit fraud or witness an SP employee act deceitfully, please notify Samaritan’s Purse leadership by calling our confidential hotline or email us at the following addresses.
Email: compliance@samaritan.org
Call or Text: 1-828-268-5780